Day 21 - 19th May 2026

Thursday

Until today most of the focus was on preparing for the Cill Beams arrival and install.

Thursday was a turning point in the project, we are no longer removing part of the old structure we are preparing for the installation of the new one.

There was a nice delivery in the carpark when I arrived sitting on the trailer of a Beaver Bridges lorry - The First Cill Beam all the way from Ayrshire!




Meanwhile in the field compound area, a second delivery was being setup!





The Cill Beams would be swung in this view! (above)


The field compound looking from the road


Cill Beam in position for lifting the next day - or was it!