Wednesday, 5 August 2026

Long time no update!

 Beaver Bridges have been back on site!

Tuesday 14 July 2026 I met with Beaver Bridges Site Agent at Broom Lane to discuss the snagging works ahead of his colleagues attending later that day.

We discussed many options for how the work would be undertaken.

The preferred option was to have something called legatto blocks on the edge of the abutments walls, where the redundant span was.  These are like concrete lego blocks!

However to install these safely you need a road closure!  To get a road closure you need a notice and traffic management, which isn't cheap.  I visited my contact at Highways in East Sussex, who agreed to provide the closure as his team would need to inspect the chevrons following the bridge strikes, this wasn't a problem we can all work in together.

Other members of the BB team arrived who explored other options, none of which were considered suitable.  The legatto blocks had become an issue as there wasn't sufficient time to prepare the abutment walls prior to them being installed.

It was a very hot day and slight tensions began to build, I retreated to the car and turned the Air Conditioning up full.  I made a call to Highways and used up all my goodwill in moving the road closure to another day.

The team return to the carpark and brief me on the options, I say the road closure can be moved, will that allow the legatto block to be installed, yes was the answer and the solution required.

Over the next few days (with a weekend in the middle) the team prepared the site and on the Tuesday installed the blocks using the lorry mounted hiab (Don't worry the lorry reversed, to avoid striking the bridge - that would've been embarassing!).  Alan our Civil Engineering Manager was on site overseeing the works and was very pleased with the outcome.








The P-Way Team arrive and chat with the BB Team, before agreeing a safe method of continuing on their journey - Thank you!


The completed works - We are very happy with the suitable edge restraint.

We could've used bricks which may have looked nicer, but would have taken longer to lay, which means a longer road closure and therefore more money.

There are still other smaller items which need completing around the site, some of which we always intended to do.

You maybe wondering where I was? - or not!

I was visiting Beaver Bridges in Shrewsbury to conclude the Compensation Event (a package of works not included in the original contract), the back of wall drainage and backfilling.

We had thought the value was too high and through email negotiations hadn't really made much progress.  I was travelling for my holiday and decided to take a detour and stay overnight in Shrewsbury in order to resolve the issue in person.

I'm pleased to say that this was worth while and importantly appreciated by the wider Beaver Bridges Team.  They know how far away it was.

I also took the opportunity to give Henry Beaver (Owner and CEO) his gift, which wasn't ready when he visited me.  Henry had told me he would be in London, but during the meeting I saw his Land Rover return to the car park.

You probably don't know but Henry is a big Land Rover fan, his office desk is a replica bonnet (slightly smaller than real size), every car needs a number plate and every CEO needs a name plate on their desk.  The answer was obvious a "fake" number plate with "HENRY" on it and in place of the dealership details "Beaver Bridges".  This was a gift from me personally (not the Railway), as I truly appreciate the help that Henry has personally given to this project.

The photos below is me handing Henry his new number plate!


The Railway also gave Henry a branded mug, tie, and guide book.  He was over the moon and thanked me very much.

When there is more to share, I will post again.

Additional Photos - taken after the update was drafted!








Best wishes

Mark D.

Thursday, 4 June 2026

4th June - Update

What's going on with the Project

 The Spa Valley Railway Project Team has met to discuss the items identified by our Civil Engineering Manager in relation to "snags" with the works.

Every project like this will have some snags, it's expected.  We've worked through what we would like the outcome to be.

Next we had a meeting with the Beaver Bridges Project Team, with some negotiations taking place.

It is expected that Beaver Bridges will return in the near future to complete these snags, so that we can then tidy up the area around the bridge, so it's more presentable.

On the 20th May 2026 Henry Beaver, the owner and CEO of Beaver Bridges visited me at Tunbridge Wells, along with Jon Smith, to discuss the project.  This was at my invitation as Henry hadn't visited during the works and I think it's something for both our organisations to be proud of.

The opportunity was taken to visit site and discuss the snags.

I and the Spa Valley Railway are very proud of the achievement and the good working relationships between both organisations.

Below is a photo of Henry and I at the bridge!


Best wishes

Mark D

Saturday, 25 April 2026

23rd April 2026

 Thursday

As you may have heard the new Broom Lane Bridge suffered it's first Bridge Strike on Thursday, to say we are devastated is an understatement.

I keep asking myself, how can someone allow this to happen, but I can't fathom an answer.

Luckily someone reported it to us, which the driver did not.  I called the company named on the side of the van and spoke to the driver.  He refused to provide his insurance details to me, which isn't good for us.

I can let you know that the Railway will pursue this, as it's not fair that we as an innocent party in the matter, are financially worse off because someone doesn't comply with Road Traffic Regulations.

Some photos of the damage below, please don't speculate any further, there's more that we aren't able to share at the moment.





Best wishes

Mark D.

Tuesday, 21 April 2026

Reopen to Passenger Services

Saturday - 18th April 2026

We reopened to passenger services on Saturday, returning our trains to Eridge for the first time since 22nd February 2026.

I was able to travel on the first round trip, travelling on the footplate for the Eridge to Tunbridge Wells West journey, what a proud moment it was.  Our humble Railway has achieved it's biggest and most significant project to date.

It was fantastic to see supporters out on the train and lineside, with everyone pleased with what has been achieved.

Well done to everyone involved, it's an incredible achievement.  There are minor "finishing" items to complete, but we are operating trains again!

Photo credit: Nick Burgess

Photo credit: Nick Burgess

Photo Credit: Toby Tankard

Photo Credit: Toby Tankard

Photo Credit: Toby Tankard

Photo Credit: Toby Tankard

Photo Credit: Toby Tankard

Photo Credit: Toby Tankard

Photo Credit: Toby Tankard

Thursday, 16 April 2026

Open to rail traffic

Thursday

The new Broom Lane Bridge is open to rail traffic - we've done it...

Beaver Bridges and Sonic Rail Services have done the Spa Valley Railway proud, it's incredible to think back on 23rd February we embarked on this massive project.


Best wishes

Mark D.

Wednesday 15th April 2026

Wednesday

I'm not involved directly with the pway reinstatement but will try to keep posting until we reopen.

Yesterday thanks to our Friends at Sonic Rail Services a lot was achieved with Ballast laid on the bridge and the beginning of sleepers and rails.

We've very nearly got our Railway reconnected.

There's still a lot of clear up work to take place, which we elected to do, in order to reduce the costs from our Contractors.

The P-Way work is being led by our P-Way Manager - Chris Hobden to whom we are all very grateful.  He is working very closely with the Railway's Civil Engineering Manager - Alan Cudlipp.

It's been amazing to witness the Railway coming together to what at one time, felt like a huge hurdle we may not achieve.  It's been great how everyone has really pulled together - Thank you!







Best wishes

Mark D.

Long time no update!

 Beaver Bridges have been back on site! Tuesday 14 July 2026 I met with Beaver Bridges Site Agent at Broom Lane to discuss the snagging work...