sorry for the lack of updates recently.
I am on a visit to Beaver Bridges Offices in Shrewsbury, but have some positive updates to share on my return.
I hope to have them ready by the weekend.
Best wishes
Mark D.
Broom Lane Bridge Replacement Project
Wednesday, 11 March 2026
Lack of updates
Monday, 9 March 2026
Day 11 - 07/03/2026
Saturday!
This was the first saturday working of the on-site works, which we'd mutually agreed with the Scouts and Adamswell House.
The purpose of the works was to install the scaffolding, to enable access to the abutment walls. This is to enable to Cill Beams to be installed.
A few rows of bricks will be removed in order to facilitate these works.
The scaffolders completed the work by early afternoon Saturday, so there was no need to work on Sunday!
Whilst the majority of the work was completed, some tidying up installing caps on some posts were required first thing Monday morning.
A few photos of the works, nothing too exciting.
Saturday, 7 March 2026
Day 10 - 06/03/2026
A day of further demobilisation of the demolition sub contractor.
Friday, 6 March 2026
Day 9 - 05/03/2026
During our weekly progress meeting - Peter Brown (Our Principal Designer) had noticed some metal plate still on the abutment walls which should've been removed. Some swift phone calls from the Beavers team on the call to the site team saw this remedied straight away.
Wednesday, 4 March 2026
Day 7 03/03/2026 - What bridge?
I wasn't on site myself, however excellent progress on the demolition took place along with the completion of the crane pad.
Monday, 2 March 2026
Day Six - A Big Day!
Today's the day that the demolition team arrived on site! We also had a new site agent for this phase of the works.
Saturday, 28 February 2026
Day four and five 26/27th February 2026
Day Four and Five
On Thursday 26th February 2026 we had our usual Project Progress meeting with all those from Beaver Bridges and the Spa Valley Railway Project Team together. We use these meetings to review progress, discuss issues and the entire project.
I conveyed my thanks to all those on site for mobilising and whilst there was one or two issues, they were swiftly resolved.
Work on the crane pad continues and some testing around the abutments have taken place.
There's been no big visual changes on site.
No exciting end to the working week, just colleagues who have worked hard on our bridge replacement.
Best wishes
Mark D.
Lack of updates
sorry for the lack of updates recently. I am on a visit to Beaver Bridges Offices in Shrewsbury, but have some positive updates to share on...
-
Second day on site was continuing with the site setup, including items arriving which got missed on Day one. The crane pad area in the Scout...
-
Day one - What a day! The Railway really came together yesterday afternoon following the last public passenger train over the existing bridg...
-
Today's the day that the demolition team arrived on site! We also had a new site agent for this phase of the works. The crane pad was p...


































