Saturday, 28 February 2026

Day four and five 26/27th February 2026

 Day Four and Five

On Thursday 26th February 2026 we had our usual Project Progress meeting with all those from Beaver Bridges and the Spa Valley Railway Project Team together.  We use these meetings to review progress, discuss issues and the entire project.

I conveyed my thanks to all those on site for mobilising and whilst there was one or two issues, they were swiftly resolved.

Work on the crane pad continues and some testing around the abutments have taken place.

There's been no big visual changes on site.

No exciting end to the working week, just colleagues who have worked hard on our bridge replacement.

Best wishes

Mark D.

No comments:

Post a Comment

4th June - Update

What's going on with the Project  The Spa Valley Railway Project Team has met to discuss the items identified by our Civil Engineering M...