Friday, 6 March 2026

Day 9 - 05/03/2026

During our weekly progress meeting - Peter Brown (Our Principal Designer) had noticed some metal plate still on the abutment walls which should've been removed.  Some swift phone calls from the Beavers team on the call to the site team saw this remedied straight away.




An example of the good working relationship that we've built up - Thank you!

As the sub contractor demolishing the existing structure had finished a little ahead of time, it was a demobilising day for them.

They had laid a protective system on the road surface to prevent damage and this was being collected by a large lorry, from Wales.


The protective mats stacked up on Broom Lane awaiting collection




The west abutment (Groombridge Side)


The east abutment (Tunbridge Wells West side)


The crane pad!