Day 14 - 10th March 2026

Tuesday

Work on the west abutment (Groombridge side) commenced using the scaffolding which was installed at the weekend.

This work is in preparation for the Cill Beam installation.

I've been told that the abutment walls are very strong and it's taking a lot to remove the brickwork.  By the end of the day it was estimated that 60% was complete.

Some photos below!










Meanwhile up in Shrewsbury further progress has been made on the concrete bridge deck!




Excellent progress being made!

No comments:

Post a Comment

Day 15 - 11th March 2026

 Visit to Beaver Bridges HQ in Shrewsbury Away from site on Wednesday part of the Project Team undertook a client visit to Beaver Bridges at...