Today is 22nd February 2026, the day before site mobilisation begins!
We've been waiting a long time for this day, our new bridge - it's really happening!
The new physical bridge is currently at the painters in Doncaster, having been fabricated in a facility in Nottinghamshire.
The plan for today is:
- Begin removal of the track over the existing bridge, following the last passenger train service.
- Track removed 5 metres each side of the bridge
The weather isn't on our side today either!
Tomorrow the road closure is put in place until early April and the site office/welfare/canteen arrives, followed by continuing to remove the track.
Thank you to all our Volunteers, supporters, donors we are all very grateful.
The Project Team is small and the pressure on us is high, however as a team we've worked very well.
If you are able to spare some funds to help, please head over to our Just Giving page - https://spvr.link/broomlane every penny counts.
I will update this as often as I can, to enable you all to follow the progress.